TG RERA Fines Sanali IT Parks ₹25 Lakh, Orders Over ₹1.19 Crore in Homebuyer Refunds

TG RERA Fines Sanali IT Parks ₹25 Lakh, Orders Over ₹1.19 Crore in Homebuyer Refunds
TG RERA Fines Sanali IT Parks ₹25 Lakh, Orders Over ₹1.19 Crore in Homebuyer Refunds
The PJ Herald | Hyderabad: The Telangana Real Estate Regulatory Authority (TG RERA) has issued a series of orders against real estate developers over unre…

Location: Miryalaguda, telangana

The PJ Herald | Hyderabad: The Telangana Real Estate Regulatory Authority (TG RERA) has issued a series of orders against real estate developers over unregistered project marketing, delayed construction, failure to honour agreements and non-delivery of properties. The decisions include a ₹25 lakh penalty against Sanali IT Parks and directions to refund more than ₹1.19 crore to homebuyers in five separate cases.

The action against Sanali IT Parks concerns its proposed Sanali The Edge residential project at Manchirevula in Gandipet mandal. The authority found violations of Sections 3 and 4 of the Real Estate (Regulation and Development) Act, 2016, relating to marketing and sale activities without the mandatory project registration.

Join the PJ NEWS WhatsApp Channel

Get important news and breaking updates directly.

Join Now

TG RERA directed the promoter to pay the ₹25 lakh penalty within 30 days and immediately discontinue advertising, marketing, booking and selling units in the project until the required registration is obtained. The decision followed complaints concerning the proposed development.

In five separate refund cases, the authority ordered Tripura Constructions to return ₹41.85 lakh, SVM Aditya Homes ₹27.16 lakh, Bhuvanteza Infra Projects ₹26 lakh, Sri Aditya Squares ₹17 lakh and BVR Infra Developers ₹7 lakh. The combined principal amount exceeds ₹1.19 crore, with applicable interest payable under the respective orders.

The cases involved issues including failure to secure statutory approvals, delays in construction, non-delivery of agreed properties and unfulfilled refund commitments. The reported orders provide for annual interest of 10.85%, with calculation periods and payment requirements determined separately for each complaint.

In another significant decision affecting a buyer in Miyapur, TG RERA directed Arine Infraa to immediately hand over Flat No. 502 in the ARINE Emerald project. The authority rejected the developer's claim for ₹6.58 lakh in additional dues, finding that the demand was unsupported by the sale agreement and registered sale deed.

The authority also directed Vasavi Realtors LLP to pay annual interest of 10.85% on ₹49.50 lakh paid by a buyer in its Vasavi Lake City East project at Hafeezpet. The interest is to run from February 7, 2025, until possession of the flat is delivered. This was an interest-for-delay direction, not an order to refund the entire ₹49.50 lakh.

The rulings highlight the financial uncertainty faced by homebuyers who commit substantial savings to residential projects but encounter delayed possession or unresolved contractual obligations. For such purchasers, timely delivery and transparent approvals can be as important as the price of the property itself.

TG RERA warned that failure to comply with its directions could lead to further penalties under Section 63 of the RERA Act. The orders underline the importance of checking project registration, statutory permissions and contractual terms before committing funds.

While the authority has issued the directions, the available reports do not establish that all refunds have already been paid or that possession has been handed over in every case. Compliance with the orders remains a matter for subsequent verification.